The following are the cash flows of two projects:

The following are the cash flows of two projects:

Year Project A Project B
0 −$ 220   −$ 220  
1   100     120  
2   100     120  
3   100     120  
4   100        


What is the payback period of each project?

Some values below may show as rounded for display purposes, though unrounded numbers should be used for the actual calculations.

Project A has a payback period of $220 / $100 = 2.2 years
Project B has a payback period of $220 / $120 = 1.8 years