Problem 9-12 NPV versus IRR [LO1, 5]
|
Garage, Inc., has identified the following two mutually exclusive projects:
|
|
Year
|
Cash Flow (A)
|
|
Cash Flow (B)
|
||||
|
0
|
–$
|
28,500
|
|
|
–$
|
28,500
|
|
|
1
|
|
13,900
|
|
|
|
4,050
|
|
|
2
|
|
11,800
|
|
|
|
9,550
|
|
|
3
|
|
8,950
|
|
|
|
14,700
|
|
|
4
|
|
4,850
|
|
|
|
16,300
|
|
|
|
|||||||
|
a-1
|
What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)
|
|
|
IRR
|
|
Project A
|
%
|
|
Project B
|
%
|
|
|
|
|
a-2
|
Using the IRR decision rule, which project should the company accept?
|
|
|
|
|
|
Project A
|
|
a-3
|
Is this decision necessarily correct?
|
|
|
|
|
|
No
|
|
b-1
|
If the required return is 11 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
|
|
|
NPV
|
|
Project A
|
$
|
|
Project B
|
$
|
|
|
|
|
b-2
|
Which project will the company choose if it applies the NPV decision rule?
|
|
|
|
|
|
Project B
|
|
c.
|
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
|
|
Discount rate
|
%
|
Explanation:
a.
|
The IRR is the interest rate that makes the NPV of the project equal to zero. The equation for the IRR of Project A is:
|
|
0 = –$28,500 + $13,900 / (1 + IRR) + $11,800 / (1 + IRR)2 + $8,950 / (1 + IRR)3 + $4,850 / (1 + IRR)4
|
|
|
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
|
|
|
|
IRR = 17.37%
|
|
|
|
The equation for the IRR of Project B is:
|
|
|
|
0 = –$28,500 + $4,050 / (1 + IRR) + $9,550 / (1 + IRR)2 + $14,700 / (1 + IRR)3 + $16,300 / (1 + IRR)4
|
|
|
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
|
|
|
|
IRR = 16.73%
|
|
|
|
Examining the IRRs of the projects, we see that the IRRA is greater than the IRRB, so IRR decision rule implies accepting Project A. This may not be a correct decision; however, because the IRR criterion has a ranking problem for mutually exclusive projects. To see if the IRR decision rule is correct or not, we need to evaluate the project NPVs.
|
b.
|
The NPV of Project A is:
|
|
|
|
NPVA = –$28,500 + $13,900 / 1.11 + $11,800 / 1.112 + $8,950 / 1.113 + $4,850 / 1.114
|
|
NPVA = $3,338.68
|
|
|
|
And the NPV of Project B is:
|
|
|
|
NPVB = –$28,500 + $4,050 / 1.11 + $9,550 / 1.112 + $14,700 / 1.113 + $16,300 / 1.114
|
|
NPVB = $4,385.47
|
|
|
|
The NPVB is greater than the NPVA, so we should accept Project B.
|
c.
|
To find the crossover rate, we subtract the cash flows from one project from the cash flows of the other project. Here, we will subtract the cash flows for Project B from the cash flows of Project A. Once we find these differential cash flows, we find the IRR. The equation for the crossover rate is:
|
|
|
|
Crossover rate: 0 = $9,850 / (1 + R) + $2,250 / (1 + R)2 – $5,750 / (1 + R)3 – $11,450 / (1 + R)4
|
|
|
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
|
|
|
|
R = 15.28%
|
|
|
|
At discount rates above 15.28 percent choose Project A; for discount rates below 15.28 percent choose Project B; indifferent between A and B at a discount rate of 15.28 percent.
|
|
Calculator Solution:
|
|
|
|
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.
|
|
Project A
|
|
|
|
|
CFo
|
–$28,500
|
CFo
|
–$28,500
|
|
C01
|
$13,900
|
C01
|
$13,900
|
|
F01
|
1
|
F01
|
1
|
|
C02
|
$11,800
|
C02
|
$11,800
|
|
F02
|
1
|
F02
|
1
|
|
C03
|
$8,950
|
C03
|
$8,950
|
|
F03
|
1
|
F03
|
1
|
|
C04
|
$4,850
|
C04
|
$4,850
|
|
F04
|
1
|
F04
|
1
|
|
IRR CPT
|
I = 11%
|
||
|
17.37%
|
NPV CPT
|
||
|
|
$3,338.68
|
||
|
Project B
|
|
|
|
|
CFo
|
–$28,500
|
CFo
|
–$28,500
|
|
C01
|
$4,050
|
C01
|
$4,050
|
|
F01
|
1
|
F01
|
1
|
|
C02
|
$9,550
|
C02
|
$9,550
|
|
F02
|
1
|
F02
|
1
|
|
C03
|
$14,700
|
C03
|
$14,700
|
|
F03
|
1
|
F03
|
1
|
|
C04
|
$16,300
|
C04
|
$16,300
|
|
F04
|
1
|
F04
|
1
|
|
IRR CPT
|
I = 11%
|
||
|
16.73%
|
NPV CPT
|
||
|
|
$4,385.47
|
||
|
Crossover rate
|
|
|
CFo
|
$0
|
|
C01
|
$9,850
|
|
F01
|
1
|
|
C02
|
$2,250
|
|
F02
|
1
|
|
C03
|
–$5,750
|
|
F03
|
1
|
|
CO4
|
–$11,450
|
|
FO4
|
1
|
|
IRR CPT
|
|
|
15.28%
|
|
No comments:
Post a Comment