adsterra.com

Wednesday, 18 October 2017

Consider projects A and B: Which project does the IRR rule suggest is best?

Consider projects A and B:

 
Cash Flows (dollars)
 
Project C0 C1 C2 NPV at 11%
A −38,000 27,400 27,400 +$8,923
B −58,000 41,000 41,000 +12,213


a. Calculate IRRs for A and B.save image

Explanation
Some values below may show  as rounded for display purposes, though unrounded numbers should be used for actual calculations.

a.
IRRA = discount rate (r), which is the solution to the following equation:

C × [10.21 10.21 × (1.21)8] = $500
IRRB = discount rate (r), which is the solution to the following equation:

$41,000 × [1r 1r × (1+r)2] = $58,000 r= IRRB= 26.55%
b. & c.
The IRR of project A is 28.30%, and that of B is 26.55%. However, project B has the higher NPV and therefore is preferred.

Calculator computations:
CF0 = −38,000
CO1 = 27,400 FO1 = 2
IRR CPT = 28.30

 
CF0 = −58,000
CO1 = 41,000 FO1 = 2
IRR CPT = 26.55
Thank you!

No comments:

Post a Comment