What is the profitability index of a project that costs $8,000 and
provides cash flows of $2,400 in years 1 and 2 and $4,400 in years 3 and
4? The discount rate is 10%.
Explanation
Some values below may show as rounded for display purposes, though unrounded numbers should be used for the actual calculations.
| NPV = |
−$8,000 + |
$2,400 |
+ |
$2,400 |
+ |
$4,400 |
− |
$4,400 |
= $2,476.33 |
| 1.10 |
1.102 |
1.103 |
1.104 |
| Profitability index |
= |
NPV / Initial investment |
| |
= |
$2,476.33 / $8,000 |
| |
= |
.3095 |
Calculator computations:
| CF0 |
= |
–8,000 |
| CO1 |
= |
2,400 FO1 = 2 |
| CO2 |
= |
4,400 FO2 = 2 |
I = 10
NPV CPT = 2,476.33
Thank you!